WORK SITE CONDITIONS
Before starting any job, the operator should perform a walk-around
inspection of the immediate work area and survey the conditions at the
work-site. The checklist should include:
- Site Activity
Other work components of the
project that are going on at the
same time or others using or
needing access to or through the
work area.
- Overhead Electrical Conductors
Utility wires or support cables that are hanging within the safe limit
of approach of the maximum vertical height or reach or the machine.
- Underground Utilities
Utility cables or pipes in or near the work area.
- Overhead/ground Level Obstacles
Overhead walkways, poles, fences, trees, manholes, etc., that will
need to be moved or avoided in order to complete the job safely and
efficiently.
- Traffic Conditions
Other machines operating in the same general area or public vehicles
that will continue to operate near the work area during the operation.
- Other Personnel
Will other workers of the general public be near or within the work
area?