9. Installing Wood Shoring
The basics on wood shoring installation
- Install shoring as soon as possible after excavating completed.
- Minimum of 2 sets of shores in a trench.
- 2 Struts on each set of uprights
- Top strut – max. 18” below surface
- Bottom strut – max. 24” up from bottom
- Shoring is installed from the top down.
- Shoring is removed from the bottom up.
- Wood shoring must be installed according to the shoring tables.
- Do not work past the point of shoring.
- Do not enter an unshored excavation.
Installing wood shoring
- Observer pm top keeps excavation under watch anytime a worker is
in the excavation.
- Excavating machine must have bucket in trench directly in from of
shores being installed.
- Machine operator must keep the workers putting in the shoring under
observation.
- Put uprights in the trench – minimum of 2 sets.
- Install the top 2 struts before placing the bottom struts.
- Place first strut no lower than 18” below the surface – keep strut
level.
- Install the second strut by
working off a ladder. Keep
vertical spacing as stated in
shoring tables. Have the bucket
of the machine in between the
uprights while the struts are
placed.
- Install lower struts – spacing as
per shoring tables. Bottom strut –
max 2′up from trench bottom.