ConocoPhillips Canada
(North) Limited
www.conocophillips.ca
ConocoPhillips Canada (North) Limited holds a 75% interest
in, and operates, the Parsons Lake
natural gas field. ConocoPhillips Canada (North) Limited
is a wholly owned subsidiary of
ConocoPhillips Canada Limited, one of Canada’s largest
oil and natural gas
exploration and production companies and a leading marketer
and distributor of crude oil,
natural gas and natural gas liquids.
Shell Canada Limited
www.shell.ca
Shell Canada Limited holds a 100% interest in, and operates,
the Niglintgak
natural gas field. Shell Canada Limited is one of the largest
integrated petroleum companies in
Canada. It is the country’s largest producer of sulphur,
a major producer
of natural gas, natural gas liquids and bitumen, and a leading
manufacturer, distributor and
marketer of refined petroleum products.
ExxonMobil Canada Properties
www.exxonmobil.com
ExxonMobil Canada Properties holds a 25% interest in the
Parsons Lake natural
gas field. ExxonMobil Canada Properties is a partnership of
ExxonMobil Canada Ltd.
and its wholly owned subsidiary, ExxonMobil Resources Ltd.
It is one of Canada’s leading
producers of conventional crude oil, heavy oil, natural gas
and natural gas liquids.
Did You Know?
The proposed Mackenzie Gas Project would become one of the
most complex undertakings in
the NWT to date:
- to assist with community consultation, the project
has staff in three regional offices.
- during the peak construction season, up to 7000 people
will work on pipeline construction
-
the pipeline system will be built in sections "or spreads" ranging
in length from 120 to 160
kilometres
- more than 40 self-sufficient camps will be needed to
house the thousands of construction
workers and support personnel
- the project will make use of four to five million cubic
metres of natural construction
material such as gravel and sand
- about 19 barge landing sites will be required to land
materials transported by barge down
the Mackenzie River – eight of these sites already
exist
- initially, four compressor stations could be built but
as new natural gas discoveries are
developed, more compressor stations may be added
- compressor stations will be monitored 24/7 from a central
operations control center
- total length of the gathering system, natural gas liquids
pipeline and natural gas pipeline is
about 1900 kilometres
- the natural gas pipeline will take gas from a processing
facility near Inuvik to an
interconnect facility in northwestern Alberta – a distance
of about 1,200 kilometres.
- 1200 kilometres is about the same distance as driving
the round trip from Edmonton to
Calgary and back twice.