PHASE II - PLANNING AND DEVELOPMENT      MID 1995 - END 1996

Recommendation

Action Required

Key
Responsibilities

Resources Required

Time Lines

Expected Outcomes


*The Working Committee should seek funding to meet financial requirements of Phase III estimated at $200,000 to $250,000.


*Working Committee assigns submission of funding applications to Executive Director
* Working Committee identifies sources of funding for federation model


*Executive Director and Working Committee


*Some financial resources may be required, however primary resource will be the time of the Executive Director and Working Committee members
* Telephone conferences, travel


*Throughout 1996 with some funding agreements secured by June of 1996 and most agreements secured by the Fall of 1996


*Substantial part of financial base for Phase III is secured






Chrow

Gibson

Omidvar